Throughout 2018, 2019, 2020, and 2021, as work continues with our design teams to build the curriculum and partnerships within each School of Study, building modifications will be made to best meet the needs of the centralized Schools of Study. Updates to the construction will be posted to this page. Please check back regularly for updates.
- New EACC Diesel and Automotive Technology building on County Road 10 – completed December 2019
- Engineering, Technology, and Innovation building broke ground September 2019 and is scheduled to be completed July 2020
- Current project at the current Elkhart Memorial is scheduled to be completed August 2020
- Renovation of current EACC to house future EHS programming scheduled to start in June 2020 and is scheduled to complete in July 2021
- Renovation at Elkhart Central scheduled to start in June 2020 and is scheduled to complete in July 2021
- Second phase of work at Memorial is scheduled to being in October 2020, scheduled to complete in July 2021
June 2020
New Building: EHS Engineering, Technology, and Innovation School of Study
Continued work on new Elkhart High School ETI Building
May 2020
Renovation to Old Band and Orchestra Area
Renovations to old band and orchestra room will be part of the new cafeteria/food service space.
May 2020
New Building: EHS Engineering, Technology, and Innovation School of Study
Continued work on new Elkhart High School ETI Building
April 2020
New Building: EHS Engineering, Technology, and Innovation School of Study
Continued work on new Elkhart High School ETI Building
April 2020
Renovation to Old Band and Orchestra Area and Painting at EHS
March 2020
New Building: EHS Engineering, Technology, and Innovation School of Study
Continued work on new Elkhart High School ETI Building
March 2020
Renovation to Old Band and Orchestra Area and Welcome Center
Renovations to old band and orchestra room will be part of the new cafeteria/food service space. The welcome center is located in the main office space.
February 2020
Renovation to Old Band and Orchestra Area
Renovations to old band and orchestra room will be part of the new cafeteria/food service space.
February 2020
New Building: EHS Engineering, Technology, and Innovation School of Study
Continued work on new Elkhart High School ETI Building
January 2020
New Building: EHS Engineering, Technology, and Innovation School of Study
Continued work on new Elkhart High School ETI Building
January 2020
New Addition: Performing Arts Wing
Addition of Performing Arts Wing to Elkhart High School (EMHS)
November 2019
New Building: EHS Engineering, Technology, and Innovation School of Study
Continued work on new Elkhart High School ETI Building
October 2019
New Building: EHS Engineering, Technology, and Innovation School of Study
Groundbreaking on new Elkhart High School ETI Building
October 2019
New Addition: Performing Arts Wing
Addition of Performing Arts Wing to Elkhart High School (EMHS)
October 2019
New Building: Elkhart Area Career Center
New Diesel and Automotive Technology Services Building
October 2019
Renovations to Welcome Center
Welcome Center/Office
August 2019
Renovations to Welcome Center
Welcome Center/Office
April 2019
Renovations to Welcome Center & Existing Pool Area (April)
Renovations to the Welcome Center/office. Continued construction on the existing EMHS pool and surrounding area, as this area is being redesigned as instructional space.
March 2019
Renovations to Welcome Center & Existing Pool Area (March)
Renovations to the Welcome Center/office. Continued construction on the existing EMHS pool and surrounding area, as this area is being redesigned as instructional space.
February 2019
Renovations to Welcome Center & Existing Pool Area (February)
Renovations to the Welcome Center/office. Continued construction on the existing EMHS pool and surrounding area, as this area is being redesigned as instructional space.
January 2019
Renovations to Existing Pool Area (January)
Existing EMHS pool and surrounding area being filled in and redesigned as instructional space. Students at Elkhart High School will use the Elkhart Aquatics Center (upon completion) as their home base for all swim events.
December 2018
Business and International Relations School of Study (December)
Main EMHS offices move to Business and International Relations space to accommodate renovations.
November 2018
Business and International Relations School of Study (Mid-November)
Business and International Relations School of Study (Early November)
October 2018
Business and International Relations School of Study
Arts & Communication School of Study